A new boiler following the existing 3 functional boilers in the heating plant. Technoprojekt prepared the planning permit documentation, the building permit documentation which included engineering, and, further, provided also a new boiler trial operation, including commissioning.

CLIENT: ENERGETIKA TŘINEC, a.s.
PROJECT IMPLEMENTATION: 2013 – 2015

WORK SCOPE:

  • Planning permit documentation;
  • Building permit documentation;
  • Arrangement of trial operation and building commissioning.