Reduction of Emission of Solid Pollutants, NOx and SO2 on the Boiler K14, E3 Heating Plant
Want create site? Find Free WordPress Themes and plugins.
A new boiler K14 will be situated at the existing area of the heating plant E3 of the company TŘINECKÉ ŽELEZÁRNY, a. s. No new sites will be occupied due to the boiler building; all lands are affected by the industrial activity. The new boiler will follow the existing 3 functional boilers in the heating plant – K11, K12 and K14; the last one will be put out of operation and dismantled when the new boiler will be fully put in operation.
CLIENT: | SES Energoprojekt, s.r.o. |
PROJECT IMPLEMENTATION: | 2013 – 2015 |
WORK SCOPE:
- Planning permit documentation;
- Building permit documentation;
- Trial operation and building commissioning.
Did you find apk for android? You can find new Free Android Games and apps.